Decision Memo Completed

Charlie Quarry Expansion Project

Umpqua National Forest Douglas, Oregon Tiller Ranger District

The project seeks to expand the current Charlie Quarry footprint approximately 2 acres to the North.

Location

Township 31S, Range 1W, Section 8 SENE

Project timeline

1
Scoping Start
04/09/2025
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical ExclusionBlm F(10) (516 Dm 11.9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Charlie Quarry Expansion ProjectDecision Signed Date: 05/19/2025
ForestsUmpqua National Forest
DistrictsTiller Ranger District
Legal Land DescriptionNot Applicable
Minerals and geology