The project seeks to expand the current Charlie Quarry footprint approximately 2 acres to the North.
Location
Township 31S, Range 1W, Section 8 SENE
Project timeline
1
Scoping Start
04/09/2025
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | Blm F(10) (516 Dm 11.9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Charlie Quarry Expansion Project | Decision Signed Date: 05/19/2025 |
| Forests | Umpqua National Forest |
| Districts | Tiller Ranger District |
| Legal Land Description | Not Applicable |