Brushy Creek Bridge Replacement
Location
Brushy Creek Bridge
Project timeline
1
Scoping Start
03/15/2008
2
Comment Period
11/14/2009
3
Decision
01/2010 (Estimated)
4
Implementation
02/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Improvements/Construction |
| Brushy Creek Bridge Replacement | Decision Signed Date: 01/25/2010 Legal Notice Date: 01/30/2010 |
| Forests | National Forests in Alabama |
| Districts | Bankhead Ranger District |