Erect two new permanent weather stations which will include 20' X 20' chainlink fenced area.
Location
Terrapin Creek Watershed and Hollins WMA along FDR 696
Project timeline
1
Scoping Start
05/07/2013
2
Comment Period
05/07/2013
3
Decision
11/2013 (Estimated)
4
Implementation
12/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction |
| Weather Station Installation Project | Decision Signed Date: 11/20/2013 |
| Forests | National Forests in Alabama |
| Districts | Shoal Creek Ranger District; Talladega Ranger District |
| Legal Land Description | Township 13S, Range 11E, Section 18 and Township 21S, Range 5E, Section 34 |