The existing culvert will be replaced with a single span bridge, with abutment walls and wingwalls designed to pass a 50-year flood event and span the bankfull width of Rush Creek.
Location
6th level HUC: Rush Creek-Brushy Creek(031601100201)
Project timeline
1
Scoping Start
05/23/2013
2
Comment Period
08/17/2013
3
Objection Period Start
10/31/2013
4
Decision
11/2014 (Estimated)
5
Implementation
02/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Road Improvements/Construction |
| Rush Creek Culvert Replacement Project | Decision Signed Date: 11/20/2014 |
| Forests | National Forests in Alabama |
| Districts | Bankhead Ranger District |
| Legal Land Description | Not Applicable |