Project timeline
1
Scoping Start
01/30/2014
2
Decision
09/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Alabama Power Company Access Roads for Existing Powerline | Decision Signed Date: 09/29/2014 |
| Forests | National Forests in Alabama |
| Districts | Shoal Creek Ranger District |
| Legal Land Description | Not Applicable |