Restoration and improvement of Upland Pine Stands using timber harvest, midstory removal, herbicide application, prescribed fire, and integrated NNIS control.
Location
Tuskegee Ranger District
Project timeline
1
Scoping Start
02/01/2018
2
Comment Period
08/19/2021
3
10/01/2021
4
Decision
10/2021 (Estimated)
5
Implementation
10/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Tuskegee Upland Pine Restoration Phase II Project | Decision Signed Date: 10/01/2021 |
| Forests | National Forests in Alabama |
| Districts | Tuskegee Ranger District |
| Legal Land Description | Not Applicable |