Due to Hurricane Sally producing large amounts of rainfall totals around the Conecuh District, the Conecuh hiking trail and bridges suffered damage. This damage created safety concerns on 4 bridges, requiring them to be replaced.
Location
Various locations along the Conecuh Hiking Trail. One on the North Loop, one on the Connector Trail and two on the South Loop
Project timeline
1
Scoping Start
06/28/2021
2
Comment Period
08/04/2021
3
Decision
08/2021 (Estimated)
4
Implementation
09/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Conecuh Hiking Trail Bridge(s) Maintenance/Repair/Replacement Project | Decision Signed Date: 08/31/2021 |
| Forests | National Forests in Alabama |
| Districts | Conecuh Ranger District |
| Legal Land Description | Not Applicable |