Decision Memo Completed

Low Pressure Soil & Water Project

National Forests in Alabama Winston, Alabama Bankhead Ranger District

Restore appropriate BMP's and control access along FS234WE to reduce sedimentation into the Sipsey Fork while providing appropriate level of access for visitors.

Location

FS Road 234WE off of Country Road 2

Project timeline

1
Scoping Start
02/16/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (20), 36 Cfr 220.6(E)(20)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Watershed Improvements
Soil & Water Project - Erosion Control - FSR 234WE Low Pressure BridgeDecision Signed Date: 06/23/2022
ForestsNational Forests in Alabama
DistrictsBankhead Ranger District
Legal Land DescriptionNot Applicable
Road managementWatershed management