Southeast Gas has submitted a special use application to install a 6-inch natural gas pipeline across national forest lands on County Road 53 in order to supply the industrial park with the needed natural gas.
Location
West of Interstate 85 along County Road 53.
Project timeline
1
Scoping Start
06/10/2024
2
Comment Period
06/10/2024
3
Decision
07/2024 (Estimated)
4
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Natural Gas |
| Southeast Gas SUP for Natural Gas Pipeline Installation | Decision Signed Date: 07/30/2024 |
| Forests | National Forests in Alabama |
| Districts | Tuskegee Ranger District |
| Legal Land Description | Section 35 Township 18N Range 24E |