1
Scoping Start
06/10/2024
2
Comment Period
06/10/2024
3
Decision
07/2024 (Estimated)
4
Implementation
08/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Natural Gas
Southeast Gas SUP for Natural Gas Pipeline InstallationDecision Signed Date: 07/30/2024
ForestsNational Forests in Alabama
DistrictsTuskegee Ranger District
Legal Land DescriptionSection 35 Township 18N Range 24E