The proposed project is to reissue a special use permit to address safety issues and for the reclamation of the area surrounding a limestone quarry.
Location
3.7 mile SW of McKee, KY Total proposed project size is approximately 5 acres.
Project timeline
1
Scoping Start
11/16/2009
2
Decision
03/2010 (Estimated)
3
Implementation
03/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Allen Company Quarry Special Use Permit Reissuance | Decision Signed Date: 03/11/2010 |
| Forests | Daniel Boone National Forest |
| Districts | London Ranger District |