Approximately 7,000 acres are proposed for the reduction/removal of the mid-story layer using hand tools to work towards 1.K-Objective1.E of the DBNF Forest Plan
Location
Locations scattered throughout the district, within the Red Bird River watershed
Project timeline
1
Scoping Start
02/12/2010
2
Decision
02/2011 (Estimated)
3
Implementation
04/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Midstory Removal | Decision Signed Date: 02/08/2011 |
| Forests | Daniel Boone National Forest |
| Districts | Redbird Ranger District |