Relocation of an existing cross country aboveground powerline to a new location adjacent to KY HWY 801. The new powerline will also be a buried line.
Location
Along KY HWY 801, north of Cave Run Lake
Project timeline
1
Scoping Start
12/15/2009
2
Decision
03/2010 (Estimated)
3
Implementation
03/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Scenery Management |
| Clark Energy Special Use Permit Amendment # 3 | Decision Signed Date: 03/03/2010 |
| Forests | Daniel Boone National Forest |
| Districts | Cumberland Ranger District |