The project will involve granting a special use permit to Grayson RECC to upgrade the existing single-phase distribution line to a three-phase, 7200-volt line and rerouting the line from the existing right-of-way (ROW) to the State Route 519 corridor
Location
Adjacent to Kentucky Highway 519 South of Morehead, Kentucky
Project timeline
1
Scoping Start
12/18/2009
2
Decision
03/2010 (Estimated)
3
Implementation
04/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Grayson Rural Electric Special Use Permit (MOR4031-02) Amendment #7 | Decision Signed Date: 03/03/2010 |
| Forests | Daniel Boone National Forest |
| Districts | Cumberland Ranger District |