Decision Memo Completed

Grayson RECC Route 519 Distribution Line Upgrade Project

Daniel Boone National Forest Rowan, Kentucky Cumberland Ranger District

The project will involve granting a special use permit to Grayson RECC to upgrade the existing single-phase distribution line to a three-phase, 7200-volt line and rerouting the line from the existing right-of-way (ROW) to the State Route 519 corridor

Location

Adjacent to Kentucky Highway 519 South of Morehead, Kentucky

Project timeline

1
Scoping Start
12/18/2009
2
Decision
03/2010 (Estimated)
3
Implementation
04/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Grayson Rural Electric Special Use Permit (MOR4031-02) Amendment #7Decision Signed Date: 03/03/2010