Kentucky Utilities needs to replace an electric tower near Mount Victory that is too low, resulting in transmission lines being too low for safety. Project will cause some ground disturbance within the current ROW. Rehab of site will occur.
Location
Between Mount Victory, Kentucky and the Rockcastle River.
Project timeline
1
Scoping Start
05/13/2016
2
Decision
05/2016 (Estimated)
3
Implementation
05/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Kentucky Utilities Special Use Authorization Amendment: Transmission Tower #157 Replacement | Decision Signed Date: 05/23/2016 |
| Forests | Daniel Boone National Forest |
| Districts | London Ranger District |
| Legal Land Description | Not Applicable |