Decision Memo Completed

Norma Harris Silt Check AML Reclamation

Daniel Boone National Forest Clay, Kentucky Redbird Ranger District

This project consists of removing sediment behind an existing gabion check dam and installing water bars to allow for proper drainage, improved aquatic habitat, and flood prevention for nearby residences. The project area is on former mine lands.

Location

On Henry Fork Road 4.8 miles from Big Creek near the town of Hyden, Kentucky.

Project timeline

1
Scoping Start
02/10/2017
2
Decision
03/2017 (Estimated)
3
Implementation
03/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityAbandoned Mine Land Clean-Up; Watershed Improvements
Norma Harris Silt Check AML ReclamationDecision Signed Date: 03/02/2017
ForestsDaniel Boone National Forest
DistrictsRedbird Ranger District
Legal Land DescriptionNot Applicable
Wildlife, fish, rare plantsMinerals and geologyWatershed management