Construction of a 2-inch gas pipeline approximately 10,946 feet long with a right-of-way width of 10 feet wide equaling 2.5 acres. The pipeline would be buried within the existing roadways at a depth of 24 inches.
Location
Bear Wallow School Road (MC-526) and four unnamed access roads.
Project timeline
1
Scoping Start
09/15/2021
2
Decision
11/2021 (Estimated)
3
Implementation
12/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Citipower Gas Pipeline Special Use Permit Amendment #1 | Decision Signed Date: 11/09/2021 |
| Forests | Daniel Boone National Forest |
| Districts | Stearns Ranger District |
| Legal Land Description | Not Applicable |