Decision Memo Completed

Hyden-Leslie Water SUP

Daniel Boone National Forest Leslie, Kentucky Redbird Ranger District

Hyden-Leslie Water has requested a Special Use Permit for use of ~ 0.06 acres of NFS Lands along Wilder Branch and Trace Fork Road to construct and maintain a 10'x10' concrete pump house and new 4" water line to existing water line.

Location

Wilder Branch 37.263782/ -83.397805 and Trace Fork Road 37.270996/-83.393967

Project timeline

1
Scoping Start
11/01/2023
2
Decision
02/2024 (Estimated)
3
Implementation
11/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Hyden-Leslie Water SUPDecision Signed Date: 02/01/2024
ForestsDaniel Boone National Forest
DistrictsRedbird Ranger District
Legal Land DescriptionNot Applicable