Crystal Broadband Network is requesting a Special Use Permit to install approx 7.22 miles of fiber optic cable across National Forest lands in Clay and Leslie Counties, along Hwy 66, 406 and 421 on existing poles.
Location
Hwy 66, 406, and 421
Project timeline
1
Scoping Start
06/20/2024
2
Decision
07/2024 (Estimated)
3
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Crystal Broadband Networks Fiber Optic Cable | Decision Signed Date: 07/03/2024 |
| Forests | Daniel Boone National Forest |
| Districts | Redbird Ranger District |
| Legal Land Description | Not Applicable |