The Proposed Action is to issue a special use permit for the construction, occupancy and use of a 230kV electric transmission line on approximately 6.4 miles of national forest system lands on the Apalachicola National Forest.
Location
South of the Tallahassee Regional Airport (near the intersection of Springhill and Bice Roads) to Substation BP-5 (southeast of the Capital Circle S.E./Woodville Highway i
Project timeline
1
NOI in Federal Register
10/14/2010
2
DEIS NOA in Federal Register
12/23/2011
3
FEIS NOA in Federal Register
03/30/2012
4
Decision
03/2012 (Estimated)
5
Implementation
04/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| City of Tallahassee Southwestern Transmission Line | Decision Signed Date: 03/19/2012 |
| Forests | National Forests In Florida |
| Districts | Wakulla Ranger District |