Replacing 219 Existing Poles and line along CR 379, SR 65, FR 101 B, FR 115, FR 123, CR 375, and FR 329
Location
CR 379, SR 65, FR 101 B, FR115, FR 123, CR 375, and FR 329
Project timeline
1
Scoping Start
10/23/2013
2
Comment Period
10/23/2013
3
Decision
12/2013 (Estimated)
4
Implementation
11/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Talquin Electric Cooperative, INC. CR379 and SR 65 | Decision Signed Date: 12/03/2013 Legal Notice Date: 12/03/2013 |
| Forests | National Forests In Florida |
| Districts | Apalachicola Ranger District |
| Legal Land Description | Not Applicable |