Decision Memo Completed

Florida Power and Light Utility Pole Replacement, Olustee

National Forests in Florida Baker, Florida Osceola Ranger District

The Osceola National Forest, proposes to issue an ammendment to an existing special use authorization to Florida Power and Light for replacement of seven existing wooden poles.

Location

The project area is located along an existing utility corridor that runs parallel to Highway 90 and Forest Roads (FR) 250A and 235A .

Project timeline

1
Scoping Start
04/30/2013
2
Comment Period
04/30/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Florida Power and Light Utility Pole ReplacementDecision Signed Date: 06/06/2013 Legal Notice Date: 08/23/2013
ForestsNational Forests In Florida
DistrictsOsceola Ranger District
Legal Land DescriptionSections 29,16, and 10, T3S, R19E