The Osceola National Forest, proposes to issue an ammendment to an existing special use authorization to Florida Power and Light for replacement of seven existing wooden poles.
Location
The project area is located along an existing utility corridor that runs parallel to Highway 90 and Forest Roads (FR) 250A and 235A .
Project timeline
1
Scoping Start
04/30/2013
2
Comment Period
04/30/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Florida Power and Light Utility Pole Replacement | Decision Signed Date: 06/06/2013 Legal Notice Date: 08/23/2013 |
| Forests | National Forests In Florida |
| Districts | Osceola Ranger District |
| Legal Land Description | Sections 29,16, and 10, T3S, R19E |