Project timeline
1
Scoping Start
09/22/2017
2
Decision
07/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Highway 40 Fiber Optic Utility Lines | Decision Signed Date: 07/16/2018 |
| Forests | National Forests In Florida |
| Districts | Lake George Ranger District |
| Legal Land Description | Not Applicable |