Connector into existing Right Of Way for City of Tallahassee transmission line. Three new utility poles will be placed with width of 106 feet.
Location
Within Existing Right Of Way(ROW) for City Of Tallahassee transmission line and southwest corner of airport adjacent to the ROW.
Project timeline
1
Scoping Start
11/06/2018
2
Decision
04/2019 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| City Of Tallahassee Solar Farm 2 Connector. | Decision Signed Date: 04/18/2019 |
| Forests | National Forests In Florida |
| Districts | Wakulla Ranger District |
| Legal Land Description | Not Applicable |