Environmental Impact Statement Cancelled

Gulf Power North Florida Resiliency Connection (NFRC) Project

National Forests in Florida Leon, Florida Wakulla Ranger District

The project proposes to connect the Florida Power and Light Company's (FPL) Raven Substation in Columbia County, Florida, to Gulf Power Company's (GPC) Sinai Substation in Jackson County, Florida.

Location

Located in compartments 201, 216, 218, 221, 222, 223,and 224 of the Apalachicola National Forest.

Project timeline

1
NOI in Federal Register
05/08/2019
2
DEIS NOA in Federal Register
09/2019 (Estimated)
3
FEIS NOA in Federal Register
11/2019 (Estimated)
4
Objection Period Start
10/2019 (Estimated)
5
Decision
12/2019 (Estimated)
6
Implementation
12/2019 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsNational Forests In Florida
DistrictsWakulla Ranger District
Legal Land DescriptionNot Applicable
Special use management