Gulf Power Company has applied for a special use permit to construct an electric transmission line on an existing utility right of way on the Apalachicola National Forest. Project information is available at www.NFRCEA.ene.com or upon request.
Location
The proposed transmission line would be co-located with the existing City of Tallahassee right of way for ~11mi in the northeastern part of the forest.
Project timeline
1
Scoping Start
12/09/2019
2
Comment Period
09/02/2020
3
Objection Period Start
10/11/2020
4
Decision
12/2020 (Estimated)
5
Implementation
01/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Proposed special use for Gulf Power Company transmission line | Decision Signed Date: 12/07/2020 |
| Forests | National Forests In Florida |
| Districts | Wakulla Ranger District |
| Legal Land Description | Not Applicable |