The Apalachicola National Forest has received an application proposing the installation of approximately 1,265 Feet of a new underground conduit with an electric cable that will run from the existing powerline pole, through an existing firebreak.
Location
Liberty county FL, Township 5 South, Range 8 West Section 9
Project timeline
1
Scoping Start
09/23/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| TALQUIN ELECTRIC HOMEOWNERS POWER | Decision Signed Date: 10/23/2020 |
| Forests | National Forests In Florida |
| Districts | Apalachicola Ranger District |
| Legal Land Description | Not Applicable |