This project includes timber harvest on approximately 8 acres associated with roadway maintenance of State Road 40.
Location
The timber harvest associated with the roadwork will occur in Compartment 221 of the Ocala NF, Seminole RD in Marion Co.
Project timeline
1
Scoping Start
10/07/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other; Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| State Road 40 Maintenance | Decision Signed Date: 10/09/2020 |
| Forests | National Forests In Florida |
| Districts | Seminole Ranger District |
| Legal Land Description | Not Applicable |