Project timeline

1
Scoping Start
01/28/2022
2
Comment Period
04/21/2022
3
Objection Period Start
06/13/2022
4
Decision
06/2022 (Estimated)
5
Implementation
08/2022 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations; Travel Management
Proposed special use for Lawhon Mill Rd. and Floyd Gray Rd. wastewater system and road pavingDecision Signed Date: 06/29/2022
ForestsNational Forests In Florida
DistrictsWakulla Ranger District
Legal Land DescriptionNot Applicable
Special use managementWatershed managementRoad management