The proposal is to rebuild an existing 60 year old single-phase, 14.4 kV overhead electric distribution line attached to wooden poles for indefinite, year-round use. Approximately 3.5 miles of single-phase, 14.4 kV overhead electric distribution line
Location
Approximately 6.3 acres (3.5Miles * 15 feet wide) of Right-Of-Way along Vilas Sumner Rd. NFR 120
Project timeline
1
Scoping Start
06/07/2023
2
Decision
12/2023 (Estimated)
3
Implementation
12/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Talquin Electric Utility Line Reconstruction | Decision Signed Date: 12/12/2023 |
| Forests | National Forests In Florida |
| Districts | Apalachicola Ranger District |
| Legal Land Description | Not Applicable |