Duke Energy proposes to replace approximately 50 wooden utility poles and replace with steel poles.
Location
Liberty and Franklin counties.
Project timeline
1
Scoping Start
05/2025 (Estimated)
2
Decision
06/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | National Forests In Florida |
| Districts | Wakulla Ranger District |
| Legal Land Description | Not Applicable |