Construct a 1-2 acre ephemeral pond for wildlife in the Abbeville dove field in compartment 180.
Location
Management Area 4 - Abbeville Dove Field
Project timeline
1
Scoping Start
03/10/2010
2
Comment Period
04/06/2010
3
Decision
04/2010 (Estimated)
4
Implementation
10/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| Abbeville Dove Field Ephemeral Pond Construction | Decision Signed Date: 04/23/2010 Legal Notice Date: 04/29/2010 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Long Cane Ranger District |
| Legal Land Description | Compartment 180 |