Proposal for the construction of three vernal ponds on the Cane Creek Dove Field site located in Compartment 60 of the Enoree Ranger District
Location
Region 8, Sumter National Forest, Enoree Ranger District
Project timeline
1
Scoping Start
08/31/2011
2
Comment Period
08/31/2011
3
Decision
09/2011 (Estimated)
4
Implementation
10/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Watershed Improvements |
| Vernal Pond Construction | Decision Signed Date: 09/02/2011 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Enoree Ranger District |
| Legal Land Description | Union County, Union, SC, Compartment 60 |