First thin and road reconstruction is proposed on approximately 20 compartments on the Sumter National Forest.
Location
Francis Marion & Sumter National Forest, Enoree Ranger District,
Project timeline
1
Scoping Start
11/16/2012
2
Comment Period
11/16/2012
3
Decision
09/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green) |
| Lower Enoree First Thinning Project | Decision Signed Date: 09/18/2013 Legal Notice Date: 09/18/2013 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Enoree Ranger District |
| Legal Land Description | Union and Newberry Counties, South Carolina |