Silvicultural Treatments consisting of commercial thinning on 6,361 acres, regeneration harvest (clearcut with reserves) on 2,146 acres and regeneration harvest ( shelterwood with reserves) on 256 acres.
Location
The project is located in the Lower Broad watershed.
Project timeline
1
Scoping Start
03/19/2015
2
Comment Period
11/09/2015
3
Objection Period Start
01/25/2016
4
Decision
05/2016 (Estimated)
5
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Timber Sales (Green) |
| Lower Broad Analysis Area | Decision Signed Date: 05/06/2016 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Enoree Ranger District |
| Legal Land Description | Not Applicable |