2012 Planning Rule Compliance
Location
Applies to monitoring on the Sumter National Forest
Project timeline
1
Scoping Start
03/17/2016
2
Decision
04/2016 (Estimated)
3
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Directive Creation/Modification; Plan Amendment |
| Changes to the Sumter Monitoring Plan, Administrative Change | Decision Signed Date: 04/29/2016 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Francis Marion and Sumter National Forest All Units |
| Legal Land Description | Not Applicable |