Additional loblolly pine stands have been located and would be treated. Other loblolly units would be changed to commercial treatments. Site prep prescribed burning and 2 additional herbicides would be added. There would be some changes to woodlands.
Location
Multiple compartments across the Andrew Pickens Ranger District
Project timeline
1
NOI in Federal Register
03/28/2018
2
DEIS NOA in Federal Register
12/21/2018
3
FEIS NOA in Federal Register
06/25/2019
4
Objection Period Start
06/25/2019
5
Decision
09/2019 (Estimated)
6
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements |
| Supplement to the AP Loblolly Pine Removal and Restoration Project | Decision Signed Date: 09/24/2019 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Andrew Pickens Ranger District |
| Legal Land Description | Not Applicable |