Construction of 3.1 miles of new trail for mountain biking and hiking from Stumphouse Passage to Oconee State Park.
Location
The proposed location is between Stumphouse and Oconee State Park along a ridge that parallels Ross Mountain Road.
Project timeline
1
Scoping Start
06/22/2018
2
Decision
07/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Palmetto Trail Ross Mountain Project | Decision Signed Date: 07/10/2019 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Andrew Pickens Ranger District |
| Legal Land Description | Not Applicable |