Installation of a single pole and associated electrical lines to enhance microwave communications with Neil Shoals Power Plant.
Location
Existing Transmission ROW off Strother Road
Project timeline
1
Scoping Start
01/25/2021
2
Decision
06/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Enoree Ranger District |
| Legal Land Description | Not Applicable |