Central Electric Cooperative will rebuild approximately a 1 mile section of transmission line on the Andrew Pickens Ranger District replacing the wooden poles with metal poles.
Location
Project is located in Compartment 26
Project timeline
1
Scoping Start
01/14/2022
2
Decision
07/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Central Electric Mt. Rest-Pickett Post 44Kv Transmission Line Rebuild | Decision Signed Date: 07/28/2022 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Andrew Pickens Ranger District |
| Legal Land Description | Not Applicable |