Dominion Energy SC proposed to rebuild 8 miles of Transmission line replacing wooden poles with metal poles. The current poles have reached their life expectancy.
Location
Edgefield and McCormick Counties Stevens Creek.
Project timeline
1
Scoping Start
09/12/2022
2
Decision
11/2023 (Estimated)
3
Implementation
11/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| Dominion Energy Stevens Creek Hook Transmission Line Rebuild | Decision Signed Date: 11/13/2023 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Long Cane Ranger District |
| Legal Land Description | Not Applicable |