The installation of approximately 1425 feet of aerial distribution lines in South Tibwin Compartment 217 in Charleston County, South Carolina to provide power to pumps that will be used to decrease the depth of current marshland.
Location
Compartment 217 Charleston County SC, South Tibwin
Project timeline
1
Scoping Start
10/02/2023
2
Decision
10/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Special Use Authorizations |
| Berkeley Electric Distribution Line South Tibwin Black Rail Project | Decision Signed Date: 10/24/2023 |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Francis Marion Ranger District |
| Legal Land Description | Not Applicable |