Henry E Brown Jr. is requesting a 50-powerline right-of-way to install approximately 3,200 linear feet of 1.5-inch copper cable and 0.5-inch fiber optic cable.
Location
Macedonia Area of Berkeley County
Project timeline
1
Scoping Start
10/02/2024
2
Decision
01/2025 (Estimated)
3
Implementation
01/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Francis Marion and Sumter National Forests |
| Districts | Francis Marion Ranger District |
| Legal Land Description | Not Applicable |