Revised Forest Plan
Location
Virginia and West Virginia, George Washington NF
Project timeline
1
NOI in Federal Register
03/10/2010
2
DEIS NOA in Federal Register
06/03/2011
3
FEIS NOA in Federal Register
12/20/2014
4
Decision
11/2014 (Estimated)
5
Implementation
01/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (1982) |
| Project Activity | Plan Creation/Revision |
| Record of Decision FEIS for the Revised GWNF Land and Resource Mgmt Plan | Decision Signed Date: 11/13/2014 |
| Forests | George Washington and Jefferson National Forest |
| Districts | North River Ranger District; James River Ranger District; Lee Ranger District; Warm Springs Ranger District; Glenwood and Pedlar Ranger Districts |