Burying of Appalachian Electric Power and CenturyLink phone lines along Forest service Road 89 approaching the summit of Whtetop Mountain and removing the existing utility poles along the buried section.
Location
Located west of SR 600 along FS 89.
Project timeline
1
Scoping Start
03/14/2013
2
Comment Period
03/16/2013
3
Decision
10/2013 (Estimated)
4
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Whitetop Underground Line Installation | Decision Signed Date: 10/29/2013 |
| Forests | George Washington and Jefferson National Forest |
| Districts | Mount Rogers National Recreation Area |