Decision Memo Completed

Hardy Telecommunications Fiber Optic Cable Network

George Washington and Jefferson National Forests Hardy, West Virginia Lee Ranger District

Construction and installation of fiber optic cabpe network on existing transmission line poles

Location

Hardy County

Project timeline

1
Scoping Start
03/25/2013
2
Comment Period
03/25/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Hardy County TelecommunicationsDecision Signed Date: 06/24/2013 Legal Notice Date: 06/24/2013
ForestsGeorge Washington and Jefferson National Forest
DistrictsLee Ranger District
Special use management