Construction and installation of fiber optic cabpe network on existing transmission line poles
Location
Hardy County
Project timeline
1
Scoping Start
03/25/2013
2
Comment Period
03/25/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Hardy County Telecommunications | Decision Signed Date: 06/24/2013 Legal Notice Date: 06/24/2013 |
| Forests | George Washington and Jefferson National Forest |
| Districts | Lee Ranger District |