Mountain Valley Pipeline, LLC is seeking a temporary use permit to conduct wetland, waterbody, cultural resource and rare, threatened and endangered spp surveys on a 2.13 mile segment for a proposed natural gas transmission crossing the JNF
Location
Surveys would occur within a 300 foot corridor along 2.13 miles of national forest system lands
Project timeline
1
Scoping Start
03/16/2015
2
Decision
04/2015 (Estimated)
3
Implementation
04/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Natural Gas |
| Special Use Permit for Routing &Survey Activities Mountain Valley Pipeline | Decision Signed Date: 04/27/2015 |
| Forests | George Washington and Jefferson National Forest |
| Districts | Eastern Divide Ranger District |
| Legal Land Description | Not Applicable |