Bury approximately 12,000 feet of fiber optic cable in an existing utility corridor.
Location
Warm Springs Mountain
Project timeline
1
Scoping Start
07/2016 (Estimated)
2
Decision
09/2016 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | George Washington and Jefferson National Forest |
| Districts | Warm Springs Ranger District |
| Legal Land Description | Not Applicable |