This project proposes to replace an existing building and shelter within the Flat Top Communication site. 2.2 miles of Forest Service Roads would be improved to facilitate the transportation of building equipment and materials.
Location
This project is located at the end of Forest Service Road 103 at the Flat Top Communication site.
Project timeline
1
Scoping Start
05/08/2019
2
Decision
06/2019 (Estimated)
3
Implementation
08/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Flat Top Communication Site Facility Upgrades | Decision Signed Date: 06/10/2019 |
| Forests | George Washington and Jefferson National Forest |
| Districts | Eastern Divide Ranger District |
| Legal Land Description | Not Applicable |