The line proposed for replacement runs for about 64.5 miles from Dominion's existing Mt. Storm substation in Grant County, W.VA to the existing Valley substation in Augusta, of which 15.5 miles crosses the George Washington National Forest.
Location
The line runs for about 64.5 miles from Dominion%u2019s existing Mt. Storm substation in Grant County, W.VA to the existing Valley substation in Augusta County, VA.
Project timeline
1
Scoping Start
03/02/2020
2
Decision
11/2021 (Estimated)
3
Implementation
12/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Mt. Storm to Valley 500kV Electric Transmission Line Replacement | Decision Signed Date: 11/03/2021 |
| Forests | George Washington and Jefferson National Forest |
| Districts | North River Ranger District |
| Legal Land Description | Not Applicable |