Kentucky Utilities Company d/b/a Old Dominion Power Company (KU/ODP) is proposing to replace 28 69kV electrical transmission line poles within an existing right-of-way across the Jefferson NF in Wise County, VA
Location
Wise County, Virginia
Project timeline
1
Scoping Start
11/04/2022
2
Decision
03/2025 (Estimated)
3
Implementation
03/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| KU/ODP Powerline Rebuild Project2022 KU/ODP Powerline Rebuild Project | Decision Signed Date: 03/20/2025 |
| Forests | George Washington and Jefferson National Forest |
| Districts | Clinch Ranger District |
| Legal Land Description | Not Applicable |